The site re-opened and the temporary fencing was moved.
The grader took the site down to grade to prepare for the lumber and truss deliveries.
Upcoming:
The lumber and trusses will be delivered.
The framers will begin framing.
The grader will connect the sewer and drain lines under the new parking area.