DECEMBER 20, 2024
There will be no weekly updates next week because of the holidays. They will resume in the New Year.
This Week:
The sprinkler contractors worked in the upper level.
The electricians worked on the can lighting for the upper level and the conduit for the lighting.
The grader began backfilling the building and retaining wall.
The HVAC crew continued making the duct in their shop.
Upcoming:
The HVAC contractor will begin installing the ductwork in the building.
The sprinkler and electrical rough-in will continue.
The grader will complete the wall and building backfill and will begin working on the gutter drainage and sewer lines.
DECEMBER 13, 2024
This Week:
The electricians continued the electrical rough-in.
The sprinkler installers continued their rough-in.
The surveyor laid out the markings for the sidewalks and curb.
Upcoming:
The HVAC crew will begin running the ductwork.
The electricians will continue.
The sprinkler piping install will continue.
The grader will backfill the retaining wall and start grading the sidewalks and curb.
DECEMBER 6, 2024
This Week:
The framers finished and the building is currently at the dry-in stage.
The sprinkler contractors installed the piping and head drops.
The plumbers finished the plumbing rough-in.
The electricians installed the conduit and wiring.
Upcoming:
The electrical and sprinkler system rough-in will continue.
The HVAC contractor will begin working in the building.
The painters will continue staining the siding materials.