MARCH 28, 2025

This Week:

The tile waterproofing and installation continued. The waterproofing was inspected and approved.

The balance of the flooring material was delivered, and the flooring was installed.

Square Peg began the interior trim.

Upcoming:

The tile waterproofing and installation will continue.

The interior trim will continue.

The flooring protection will be applied over the finished flooring.

The site will be organized and cleaned up.

The interior trim material logistics will continue.

The plasterboard will be hung and prepped for the plaster.

MARCH 21, 2025

This Week:

The gutter and downspout installation was mostly finished.

The tile flooring in the bathrooms continued, and the tile was set in the laundry rooms.

The flooring material was delivered and set in the house.

The flush mount drywall fan vents and remaining areas were finished and sanded.

The exterior siding and trim were completed to 90%, leaving the garage faces and front door to be trimmed out in a few weeks.

Upcoming:

The deck drain gutters will be finished.

The flooring, tile, wood veneer paneling, and interior wood trim installation will continue.

MARCH 14, 2025

This Week:

We had an onsite meeting and solidified the interior finishes, exterior railings, and cabinet layouts.

The front entry door frame and side lights were delivered, installed, and protected.

The stair treads were installed and protected.

The exterior porch trim and siding were completed.

The drywall on the lower level continued.

The tile and shower surfaces were prepped, and the layouts and transition details were confirmed.

Upcoming:

The tile prep and installation will continue.

The exterior trim will continue.

The interior paint prep will begin.

The flooring materials will arrive, and the prep for the flooring install will begin.

MARCH 7, 2025

This Week:

The exterior siding and trim continued on the main-level porch and was completed on the lower level.

The drywall crew hung the last of the gypsum board.

The painter applied some sample whites to the wall and ceiling for review.

We continued working on the trim details, material ordering, and subcontractor scheduling.

Upcoming:

The tile prep will begin.

The drywall crew will finish the taping, mudding, and finishing of the drywall.

The stair tread will be installed.

The front entry door will be installed.

The entry door protection will be installed.

The painters will begin their prep.

The siding and main-level exterior ceilings will be installed.