JUNE 27, 2025

This Week:

The graders completed the drainage lines and stone dispatches behind the garage, in the lower meadow, and along the north wing of the house. They set the power line conduit, gas piping, and generator conduit in the ground behind the retaining wall. They also seeded and laid straw and straw matting across the disturbed ground.

The cedar closets were installed to 85% completion.

The drywall was completed, and the dust was removed for the painters.

The mirrored ceiling in the piano bar was templated. The primary suite countertops, game room tops and backsplashes, and the screened porch grill counter and backsplash were templated.

Another cache of appliances was delivered.

Upcoming:

The trim crew will re-stage on the main floor and will begin hanging the doors and applying the bases and cases.

The exterior drainage, grading, and driveway will continue.

The painters will begin prepping the lower level for trim and applying the second coats to the walls.

The exterior trim crew will screen off portions of the lower deck and spa.

The site will be cleaned.

JUNE, 20 2025

This Week:

The stucco was applied to the foundation walls and the retaining wall.

The interior cabinets were installed in the primary bathroom, laundry, closet hall, and game room.

The lower-level case, base, and trim were completed to 85%.

The lower-level aromatic cedar closet installations began.

The last of the materials and finish surface protection was applied.

The site and interior cleanup continued.

The drywall crews pushed forward on the remainder of the piano room and areas on the main level.

Upcoming:

The piano room and other drywall surfaces will be completed.

The casework will be installed in the piano bar.

The cedar closets will be finished.

The site and grading work will continue around the house.

The upper-level doors and casing will begin.

JUNE 13, 2025

This Week:

The graders placed stone in the drainage dispatches around the back of the house. They fine-tuned the grade and protected the area from the rain.

The Square Peg continued working on the lower-level base, case, and doors.

The mudding and sanding continued in the piano room.

Several contractors prepared quotes for the window cleaning.

The prep work for the stucco began on the original concrete foundation.

We continued coordinating with the upcoming subs and finish contractors.

Several of the slab surfaces and vanities were installed.

Upcoming:

The drywall will continue in the piano room.

The painting will continue.

The stucco will continue, and the stone punch items will be addressed.

The lower-level trim, cedar paneling, and casework installation will begin and continue.

We will continue cleaning, removing the debris, and scheduling the finish contractors.

The grading will continue around the back of the house.

JUNE 6, 2025

This Week:

The trees felled during Hurricane Helene were removed.

The grader cleaned up the back side of the house.

The existing driveway was removed and backfilled with crusher run gravel for a temporary and clean surface.

The kitchen wall paneling was completed.

The cabinets were set for the slab countertop templating.

The counters, island, and primary fireplace were templated.

The piano room drywall was reworked, and the finishing began.

The materials were delivered and staged inside the house.

The lower-level trim continued.

The exercise room floor was installed.

Upcoming:

The driveway will continue to be cleared out and prepped for the final grade and pavers.

The drywall will continue in the piano bar.

The trim will continue on the lower level.

- primary shower slabs will get installed

- lower level vanities will go in