JULY 25, 2025
This Week:
All of the furniture was successfully delivered and installed.
The elevator technicians were on site for the duration of the week, terminating control wiring and performing final setup tasks in preparation for the upcoming County inspection.
The railings were delivered, and installation began promptly. The fabricators made significant progress, with the interior railings now nearing completion.
The appliances were installed, marking another step toward finalizing the interior spaces.
Upcoming:
The painter will continue work on the railing finishes and begin addressing touch-ups related to the recent furniture installation.
Final glass cleaning and interior touch-up cleaning are scheduled for completion.
The remaining parking signs and pavement striping will be installed in preparation for the final city inspection.
We will proceed with scheduling the final Certificate of Occupancy inspection with the County.
Once the elevator technicians complete their work, the elevator company will coordinate the state inspection.
JULY 17, 2025
This Week:
The furniture was delivered. The installation crew made solid progress with both assembly and placement throughout the space.
The electricians completed work in the elevator shaft and coordinated a successful factory start-up for the lighting control system.
The painter finished painting the exterior columns.
Additionally, the kitchen cabinetry installation has been completed.
Upcoming:
The furniture installation will continue.
The interior painting inside is nearing completion, with only a few rooms and the stairwell remaining.
The interior and exterior railings will be installed.
Final inspections with the city, county, and fire marshal will be scheduled soon.
JULY 11, 2025
This Week:
The painters finished the minor wall patching and applied the final coating to the walls.
The cabinet maker completed the cabinetry in the workroom and kitchen.
The granite countertops were installed.
The electrical troubleshooting and IT work continued.
The graders finished the final clean-up around the exterior of the building.
The fire alarm systems were tested.
The elevator contractor finished troubleshooting the equipment.
The HVAC systems were tested.
Upcoming:
The final cleaning and painting will continue.
The interior and exterior railings will be installed.
The furnishing move-in will begin.
A replacement countertop will be installed in the kitchen.
JULY 3, 2025
This Week:
The electricians continued installing the various lighting systems, the timer panel, and the meeting room lighting controls.
The graders paved the balance of the path to Probart Street.
The toilet accessories and door hardware were installed.
The painters continued the final painting.
The steel fabricators completed the edge metal for the stairs.
The HVAC testing and balancing were completed.
Upcoming:
The final painting will continue.
The cabinetry for the workroom and kitchen will be completed. The countertops will be installed on all cabinetry.
The elevator install will be completed, and the state inspection will be scheduled.
The stair railings will be measured, drawn, and fabricated.
The cleaning and window cleaning will begin.