JUNE 27, 2025
This Week:
The electricians continued working on minor tasks and testing the systems.
The HVAC contractor began testing the air conditioning.
The painters prepped the upstairs offices and began painting the finish coat on the walls.
The door hardware install is nearing completion, and the toilet accessory install began.
The steel contractor worked on the edge metal on the stairs.
The pathway below the dam was graded.
Upcoming:
System testing for the HVAC and electrical units will continue.
The plumbing fixtures install will be completed.
The painting, and the toilet accessories install will continue.
JUNE 20, 2025
This Week:
The graders continued cleaning up around the building and placed the topsoil and mulch.
The mason laid the block at the Broyhill porch for backfilling the curb. They installed some stone edging in a few key places around the building.
The elevator installation continued.
The electrician installed some of the lighting controls and miscellaneous trims.
The flooring contractor began installing the carpet.
The door hardware was installed.
The gutter installation continued.
The power company began working on the final power.
The plumbers installed the drinking fountain and mop sink and made a final air test to turn on the water in the building.
Upcoming:
The gutter work will continue.
The final power will be installed.
System testing will begin on the HVAC.
The carpet install will be completed.
The stair metal and railings will begin.
The final painting will begin in the completed offices.
The balance of the cabinets will be installed, and the counter templating will occur.
JUNE 13, 2025
This Week:
The graders backfilled the walking path. They backfilled and dressed up around the building as well.
The trim carpenters finished.
The ceiling contractor completed installing the last of the tiles around the sprinklers.
The plumbing trim-out continued.
The electricians continued to trim out and troubleshoot.
The gutter contractor began installing the gutters.
Upcoming:
The electrical and plumbing trim-out will continue.
The underground power from Duke Energy will be installed.
The graders will finish their work around the building.
The carpet installation should begin.
JUNE 6, 2025
This Week:
The section of road in front of the school and the path to the lower lake dam were paved.
The elevator contractor installed the wiring and controls.
The electricians worked on the service entry, lighting, and miscellaneous tasks.
The plumber installed the sinks and toilets.
The trim carpenters continued on the trims and battens.
The stone masons completed the stone work.
The ceiling contractor installed the ceiling tiles.
The power company set the new pole and transformer for the building.
Upcoming:
The elevator cab will be installed.
The carpet and flooring will begin.
The trim carpentry will continue.
The electrical trims will continue.
The cabinets will be installed, and we will template for countertops.