MAY 31, 2024

This Week:

The framing crew continued to set and place the roof trusses. They also began the timber framing.

The concrete crew corrected some of the concrete areas and the erosion control measures will be stabilized by the end of the weekend, weather permitting.

In the office, we continued scheduling the next set of trades.

Upcoming:

The roof trusses will be set to completion and the crew will start sheathing these areas of the roof framing that are complete. The crew will begin stick framing the portions of the roof structure that were not in the scope of the truss designer’s manufacturers.

MAY 24, 2024

This Week:

The framing carpenters began the roof framing. The roof trusses were received and the installation began.

Upcoming:

The carpenter will continue installing the roof framing members and will start applying the roof sheathing.

MAY 17, 2024

This Week:

The main level walls, front entry walls, and critical truss bearing points were identified, framed, and properly braced.

We met with several service providers for the propane fuel tank installation.

The Tyvek representative examined the install and progress.

In the office, we coordinated the truss delivery and crane support for next week. We continued ordering the proper hangers and hardware for the roof systems and associated connections.

Upcoming:

The roof trusses will be delivered, organized, and set.

All of the necessary walls will be braced and the trusses will be hand-placed in strategic locations ahead of the crane next week.

MAY 10, 2024

This Week:

The framers continued to frame the main-level walls and prepped the roof-bearing systems. They began framing out the underside of the elevated slab as it provides some shelter from the storms and they continued installing the Tyvek wrap.

In the office, we confirmed the truss designs and released them for fabrication.

Upcoming:

The framers will finish the underside of the elevated slab framing, build the temporary stairs, and finalize the wall systems for the roof trusses. They will continue to install the Tyvek weather barrier system.

MAY 3, 2024

This Week:

The framing crew continued framing and sheathing the main-level walls and began running the Tyvek moisture barrier on the exterior walls.

In the office, we reviewed and updated the truss drawings and layouts. We continued to receive quotes and update the working budget.

Onsite, we met with the interior trim contractor to confirm the framing openings and interior trim details.

Upcoming:

The framing crew will continue to sheath and run Tyvek on the exterior walls and frame out the elevated garage deck. A few lower-level walls in the exercise room will be framed and they will build out a temporary set of stairs.

We will continue to coordinate with the upcoming subcontractors and review the estimate.