NOVEMBER 14, 2025

This Week:

The house received its final cleaning.

The lighting controls and smart home systems were configured with the hardwired systems.

The mirrors on the bar ceiling were installed.

The primary fireplace received the steel apron.

The mirrors were hung throughout the house.

The windows were cleaned.

The chimney shroud was set.

The furniture and housewares were delivered and staged by Platt Home.

Upcoming:

The gutters will be cleaned, and the leaves will be removed from the decks.

The house will be ready for move-in!

NOVEMBER 7, 2025

This Week:

The landscaping was completed.

The smart home system was configured.

The mirrors were installed on the ceiling in the bar.

The garage was finished with epoxy.

The window cleaning began.

The final painting and touch-ups were completed.

The electrical punch items were completed.

The Amuneal shelving was built.

The kitchen chandeliers were hung at the final heights, and the decorative lights were installed.

The spa surround was completed.

The post-construction cleaning was finished.

Upcoming:

The windows will receive their final cleaning.

The furniture will be delivered and installed.

The mirrors will be hung.

The porch screens will be installed.

The chimney shroud will be set.

The house will be ready for move-in!