october 31, 2025
This Week:
We completed the scope of work for permit 23-06166 and were granted a formal CC and CO.
The spa was filled, and the testing started.
The plumbing was completed, and the final inspection was approved.
The electrical final inspection was also approved.
The landscapers installed the plants and laid mulch.
The irrigation system was rough-installed.
The grading permit was finalized and approved.
The remaining decorative lights were hung.
The post-construction cleanup has begun.
Upcoming:
The lighting, electrical, and AV system troubleshooting will wrap up.
The cabinetry panels and hardware will be finalized.
We will start to trim out the bar with the custom shelving.
The LP tanks will be connected.
We will test the heat systems, gas-fueled fixtures, and components.
The windows will get cleaned.
The garage will get cleaned out and the floor epoxied.
The punch list will get checked off across the trades.
Post-construction cleaning will continue.
october 24, 2025
This Week:
The big brass door was installed.
The kitchen cabinets were trimmed with brass.
The range hood and insert were installed.
The primary fireplace was finished.
The cabinet hardware installation continued.
The gas was tied into the fire table and griddle.
The alarm system trim-out began.
The landscaping neared completion, with irrigation to follow next week.
The decorative lighting installation began, and the tape light configuration continued.
The tile work punch list was completed.
Site clean up continued.
Upcoming:
Inspections will begin on Monday.
The decorative lights and mirrors will be placed, with help from Platt Home.
The plumbing fixtures will get tested.
The AV systems will start up.
The painters will begin final touch-ups.
Flooring and other finished surfaces will be uncovered and cleaned.
Final punch list items will be completed.
OCTOBER 17, 2025
This Week:
The driveway was paved.
The electricians began installing the electrical tape lighting and continued the trim out. The bathroom sconce installation also began.
The steel handrail for the retaining wall was installed.
The painters applied the final coats on the lower level and stained the remaining wood.
Upcoming:
The front door and lower-level bear door will be installed.
The cabinetry will be trimmed out with the crown, hardware, and toe kick throughout the house.
The painters will continue the final coats.
The house will receive full power, and the HVAC will be started.
The primary fireplace will be completed.
The last of the tile work will be finished.
The water will be turned on, and we will start testing the plumbing systems.
OCTOBER 10, 2025
This Week:
The lower-level final coats of paint were nearly completed.
The shower glass was installed in the exercise bath.
The mirrors were installed in the lower primary bathroom and hall.
The electrical systems, lights, and receptacles were tested and troubleshooted for issues.
The spa was started on the lower deck, and we began testing the system components.
The primary fireplace surround installation began.
The washers and dryers were installed.
The bathroom vanity trim installation continued.
The generator was set and connected. And the gas was hooked up.
Upcoming:
The pavers will be installed next week.
The water will be connected and tested throughout the house.
The painters will begin the final coats and stains on the balance of the unfinished surfaces upstairs.
The plumbing trim and fixtures install will continue.
The final appliances will be installed.
The electrical trim install will continue.
The site cleanup will continue.
OCTOBER 3, 2025
This Week:
The electricians continued testing the lighting and power systems and installed the track and tape light where still necessary.
The interior trim crews installed the balance of the interior doors, base trim, and window shade valances.
Heirloom's glass railing was installed around the spa on the lower deck. They also installed the brass cabinet doors in the kitchen.
The city set the water meter out front, and the HVAC team completed the gas piping in and outside the house.
The casework and slabs were installed on the first floor.
Upcoming:
The interior trim crew will install the window shade valance covers with possible minor punch items remaining.
The primary fireplace will be installed.
The electricians will install the last of the track and tape lights in the cabinets and bar.
The leftover materials and building debris from the interior and exterior will be cleaned up.
Painting will resume.
The water will be connected to the house, the HVAC systems will be turned on, and we will start the system testing.