SEPTEMBER 26, 2024

This Week:

The framing continued. The framing crew built and stood about 40% of the lower-level walls.

Upcoming:

The framers will continue.

SEPTEMBER 20, 2024

This Week:

The grader installed a sewer manhole and ran most of the sewer line for the Dean’s house and Harmony Hall.

The framers began the layouts.

Upcoming:

The framing will continue.

SEPTEMBER 13, 2024

This Week:

We ordered materials, scheduled the upcoming subcontractors, and finalized the submittal reviews.

The grader installed the storm drain boxes and filled in the open area with gravel.

Upcoming:

The framer will begin the lower-level framing.

SEPTEMBER 6, 2024

This Week:

The grader began grading the parking lot and re-routed the electrical feed to Harmony Hall. He installed drain boxes and piping in the courtyard.

The lumber and hardware deliveries for the first-floor framing were delivered.

Upcoming:

The framing will begin on the lower level.

The grader will continue working on the sewer lines from Harmony Hall.